Renovation Updates for 1/20
The Great Renovation continues this week with a full complement of tradesmen for carpentry, masonry, insulation, mechanical, electrical and site work. The north entrance vestibule canopy pad was poured, water and waste lines were installed in the ADA bathroom at north foundation and stubbed through the historic foundation wall into the basement, window and door
Renovation Updates for 1/13
The Great Renovation continued this week with a full complement of trades on the job after a well-deserved holiday break! Mechanical work included extending the boiler chimney up through the roof of the stair tower/elevator shaft which enabled the finishing touches of exterior framing and sheathing to be completed on the east side. Mechanical also
Renovation Updates for 1/7
The Great Renovation continued at a slow pace this past week as contractors were still out on holiday. However, some work did continue on the south addition stair tower installing landings, stringers and starting to install treads and risers. Won’t be long until the stairs will be useable to access from the basement to the
Renovation Updates Dec 2023
12/28 The Great Renovation continues this week albeit with small crews through the holiday season. The south addition windows have all been installed, flashed and sealed against the weather, a major milestone to enable mechanical and electrical rough-into proceed. The south stair tower stairs framing has begun with landings installed and stair stringers started. Wall
Renovation Updates 11/23
Good Morning and Happy Thanksgiving to all. Although a short week, the Great Renovation continues with framing of the second floor of the south addition along with the elevator shaft and stairwell. The back door exterior concrete pad was poured and exterior door frame installed. The sidewalk section along Franklin Street that was removed to