The Great Renovation continues this week with a full complement of tradesmen for carpentry, masonry, insulation, mechanical, electrical and site work. The north entrance vestibule canopy pad was poured, water and waste lines were installed in the ADA bathroom at north foundation and stubbed through the historic foundation wall into the basement, window and door […]