The Great Renovation continued at a slow pace this past week as contractors were still out on holiday. However, some work did continue on the south addition stair tower installing landings, stringers and starting to install treads and risers. Won’t be long until the stairs will be useable to access from the basement to the third level! Some work did progress on the north main entrance vestibule filling in the foundation with stone in preparation to pour the finish slab that will be the precursor to begin framing the ADA restroom and vestibule in addition to electrical rough-in in the interior. Hopefully the full crew for carpentry, mechanical, plumbing and electrical will all be present and accounted for this coming week!