The Brandon Free Public Library Great Renovation continues this past week with structural reinforcing of the first floor and second floor to receive the book stacks in the new arrangement. The excavation for foundations on the south side for the new elevator, stair tower and office continue. A good weather outlook for the next week should see some concrete placement for footings and foundation walls on the south side. Materials are being delivered nearly every day to enable work to move forward. Windows, doors and the elevator have been received and are all in storage awaiting their turn to be installed. Keep that sun shining for the next couple of weeks!!
-Bruce Ness